Currently 34% of the required distribution pipeline has been installed. The company will Install residential and commercial Customer service lines along the distribution system as requested by business and homeowners along The route. If you have not already done so Please print a service application from this website and send it to our corporate address.

Installing 6”Dia. HDPE distribution main on Waterford Road. Bridgewater Township Susquehanna Co. (below)

Construction_1

Stringing heat fused 4” Dia. HDPE distribution main on Turnpike Road. Bridgewater Township Susquehanna Co. (below)

Construction_2

Installing 4”Dia. HDPE distribution main on High School Road. Bridgewater Township Susquehanna Co. (below)

Construction_3

Building meter and regulator gate station on Puzos Road. Bridgewater Township Susquehanna Co. (below)

Construction_4