Currently 34% of the required distribution pipeline has been installed. The company will Install residential and commercial Customer service lines along the distribution system as requested by business and homeowners along The route. If you have not already done so Please print a service application from this website and send it to our corporate address.
Installing 6”Dia. HDPE distribution main on Waterford Road. Bridgewater Township Susquehanna Co. (below)
Stringing heat fused 4” Dia. HDPE distribution main on Turnpike Road. Bridgewater Township Susquehanna Co. (below)
Installing 4”Dia. HDPE distribution main on High School Road. Bridgewater Township Susquehanna Co. (below)
Building meter and regulator gate station on Puzos Road. Bridgewater Township Susquehanna Co. (below)
About Leatherstocking:
Leatherstocking Gas Company is a 50/50 partnership between Corning Natural Gas Corporation and Mirabito Holdings, Inc. Together we have over 190 years in serving the region with natural gas and other energy products. Contact us:
(877) 451-9276 “WARM”
lgcinfo@leatherstockinggas.com